• Skip to main content
  • Skip to footer
  • Home
  • About
    • MyPE Copyright Terms
    • Authors
    • Deals
  • Info
    • Accommodation
    • Classified Adverts
    • Directory
    • Essential PE Numbers
    • Flight Schedules
    • Forex Converter
    • PE’s Online Radio Stations
      • Algoa FM
      • Bay FM
      • iFM
      • Kingfisher FM
      • MannMade Radio
      • Madibaz Radio
      • Umhlobo Wenene
    • Podcasts
    • Shipping
    • Street Map
    • Tides
    • Ward Details
    • Ward News
    • Weather
  • Contact
    • Advertising on MyPE
  • Submit
    • Blogger
    • 5 Quick PE Questions
    • Entertainment
    • Events
      • Add your Port Elizabeth event
    • Letter to the Editor
    • Lost and Found
    • Movers and Shakers
    • News Article
    • PE Videos
    • Photographs
    • Recipes
    • Traffic Hooligan
    • Say NO
  • Dam Levels
  • Advertorial
  • Business
  • NMBRA
  • NMB Rates
MyPE

MyPE

Community Business Directory, Event Listings, News and Views from Gqeberha, Nelson Mandela Bay

Duvha Power Station – an Exercise in Incredulity

26 March 2011 By Alan Straton

An e-mail is doing the rounds showing the damage (some would call it ‘destruction’) to Unit 4 of Eskom’s Duvha Power Station. Duvha is located approximately 15 kilometres east of Witbank in Mpumulanga.

Construction of the Duvha Power Station commenced in November 1975 and final commissioning took place in 1984. Duvha cost R1.6 billion to build, its chimneys the largest freestanding concrete structures in Africa and its mine the largest open-cast colliery in the Southern Hemisphere.

Duvha’s safety record shows that it has been awarded NOSCAR status twice by the National Occupational Safety Association (NOSA). The last award was made in March 2001.

On 8 January 2003, the Unit 2 generator exploded whilst being returned to service after a malfunction. On the the 9 February 2011 Unit 4 failed catastrophically while performing over speed testing. The units are over speed rated at 3600rpm and the last recorded speed before failure was 4250rpm.

The official statement after the 9 February 2011 failure read as follows:

Repairs to Eskom’s Duvha Power Station to Take Time

February 11, 2011 – Eskom has warned that a unit which burst into flames this week at Eskom’s Duvha Power Station during a routine test will take extensive time to repair. Eskom spokeswoman Hilary Joffe said Unit 4 of Eskom’s Duvha Power Station was “damaged last night in the course of a routine test. No one was injured but the unit is expected to take extensive time to repair,” she said.

Joffe said the other five units of the 3,600 MW Duvha power station were running normally and the national grid remains in ‘green’ status, meaning that Eskom is generating enough power to satisfy the demand in the national grid. The incident happened when the 600 MW units at Duvha had been taken off load to perform a required turbine test.

“This is a statutory test that is carried out in every power station. In the execution of the test, the protection of the unit failed, causing severe mechanical damage and starting a fire, which was brought rapidly under control by the power station’s fire team,” said Joffe.

Eskom have since launched a “technical review ” of the incident. Eskom’s divisional executive for power-generation, Thava Govender, said: “The technical review is aimed at finding the cause of the unit failure, so that we may take appropriate action to prevent similar incidents in future.” Source: Nthambeleni Gabara at BUA News agency.

According to the note attached to the circulating e-mail three layers of protection failed, Unit 4 will be shut for at least 18 months and a new unit will cost around US$100 Million according to some estimates.

$100 Million ………. Now you know why the funding to the Youth League was cut, Julius.

Before you look at the images (which are purported to be genuine) stop and consider these ‘spin doctor’ statements from the above release:

  • “burst into flames” – the normal man will think fire and some melted components.
  • “extensive time to repair” – again the normal man will think three months.
  • “the protection of the unit failed” – a circuit breaker failed to trip?
  • “technical review” – again the normal man thinks, no big sweat, no mopping up, no disaster or as Roland likes to say; “No CRISIS”
  • “so that we may take appropriate action to prevent similar incidents in future” – a small cause for concern here, does this mean we are expecting other units to fail?

Methinks the fine line of being economical with the truth and lying has been overstepped here. A bit like calling the recent Japanese Tsunami; “A Big Wave”!

The fact that all the EXIF data was removed from the images below is disturbing as we cannot do a simple means test such as checking the date the images were taken to prove that they are are genuine (or as close to genuine as possible):

To me it looks serious and not at all like a ‘fire’
The wear and destruction is plainly visible
Looks expensive to fix
A fire doesn’t make projectile size holes in a roof like this
Unit 4 – See Image 1 – Duvha for comparison
Unit 4 – See Image 1 – Duvha for comparison
Unit 4 – See Image 1 – Duvha for comparison
Duvha Unit 4 after the ‘fire’
Duvha Unit 4 before the ‘fire’
The following two tabs change content below.
  • Bio
  • Latest Posts
My Twitter profileMy Facebook profileMy Google+ profileMy LinkedIn profileMy Flickr profileMy Pinterest profile

Alan Straton

Chief Cook, Bottle Washer and Broom Mechanic at MyPE
Passionate about Port Elizabeth and definitely NOT packing for Perth. Alan's ethos is epitomised in the words of Nelson Mandela; "I have fought against white domination and I have fought against black domination. I have cherished the idea of a democratic and free society. If need be, it is an ideal for which I am prepared to die." See more articles by Alan.
My Twitter profileMy Facebook profileMy Google+ profileMy LinkedIn profileMy Flickr profileMy Pinterest profile

Latest posts by Alan Straton (see all)

  • Festive Shopping Made Simple at Solly Kramer’s Parkhurst - 11 November 2026
  • Kasi Republic Brings Kwaito, Kasi Cars and Ispantsula Style to Riversands Farm Village This Reconciliation Day - 11 November 2026
  • Before the Out-Of-Office Goes On: Preparing Your Business for Year-End - 11 November 2026
  • Towa Gives Festive Season Retailers Back Office Insight From Any Location - 11 November 2026
  • Freeman House Recovery Explains the Path From First Call to Admission - 11 November 2026

Filed Under: Editorial Tagged With: duvha power station, eskom

Reader Interactions

Comments

  1. Theking1 says

    28 March 2011 at 1:40 pm

    I get the distinct impression that the damage was not an accident, but wilful. No doubt, money will have to be spent to fix this – follow the trail…

  2. puzzling says

    29 November 2011 at 9:16 am

    Update to this in November 2011. See http://www.fin24.com/Companies/Industrial/Eskom-reports-600MW-electricity-shortage-20111127

    • Alan says

      29 November 2011 at 9:26 am

      Thanks for the Duvha update – very interesting.

  3. BigBlue says

    21 November 2015 at 4:08 pm

    Uneducated knuckledragging goons cannot operate and maintain a sophisticated power plant.

    Not placing a time limit on BEE/AA/EE is an admission of inferiority.

Footer

RSS Straton Electrical

  • Open Cycle Gas Turbine Usage
  • Flattening the curve – What Every Solar Installer Needs to Know
  • Why you shouldn’t leave a charger plugged in when not in use
  • How do I check if an Electrician is properly registered in South Africa?
  • Easy Electrical Troubleshooting for Humans
  • Water – If You Cannot Measure It Then You Cannot Manage It
  • Tips To Survive Loadshedding
  • Eskom’s Top 50 Electricity Saving Tips

RSS MyPE Business News

  • NMBBC On Budget 2025
  • Leading Business Minds Set to Headline Chambers Annual General Meeting
  • Bay of Opportunity Portal
  • Bay of Opportunity Ambassadors Programme to Promote the Bay and Attract Investment
  • 6 Decades of Trucking
  • Thermal Camera Installed at Redhouse Substation
  • Finalist in the 2025 South African Car of the Year
  • Joining hands to create a lasting impact to St Albans Primary School

RSS MyPR Press Releases

  • Your Press Release Is in Good Company
  • Top 5 Reach Checks
  • LFC Construction Publishes Guide to Choosing Between Block, Gabion and Concrete Retaining Walls
  • Sealtek Cape Publishes Guide to Metal Roof Restoration as a Practical Alternative to Replacement
  • Kasi Republic Brings Kwaito, Kasi Cars and Ispantsula Style to Riversands Farm Village This Reconciliation Day

How you may use MyPE content © 2026 MyPE · Gqeberha, South Africa | Privacy Policy | MyPE Ads and Media Kit