As at 27 August 2024, significant progress has been made in the ongoing construction and restoration efforts. The contractor has successfully planted and assembled all 52 required wooden poles.
The Eskom team has completed restringing conductors on one section towards Summerstrand and removed one circuit from the lattice steel structure into a new wooden pole structure.
Additionally, the transformer at the South End substation has been energised and is currently undergoing a load test from 19:00 to 21:00. Following this test, an official load reduction schedule is provided. We appeal to residents to be patient and use essentials as power is still unstable because of demand.
For 28 August 2024, the plan includes starting the conductor stringing and installing stay wires to enhance the stability of the structures and high-voltage lines. However, due to unfavourable weather conditions forecast for 28 August 2024, construction work may be affected. Despite this, the construction team on site remains committed to completing the project by Sunday, 01 September 2024.
Our team remains dedicated to ensuring timely completion and maintaining a high standard of work, demonstrating our competencies and sense of urgency in addressing the needs of the community.
Updates will be provided to keep you informed as new developments emerge.
NMB Communications
Latest posts by NMB Communications (see all)
- Join The Celebration - 26 February 2025
- 6 Municipal Employees Supended - 15 January 2025
- Fishwater Flats Wastewater Treatment Plant Work Progressing Well - 10 January 2025
- Kliprand Protest Brings Action - 7 January 2025
- Mayor Tells Us Why We Had a Successful Festive Season in Nelson Mandela Bay - 6 January 2025