Plans to relocate flood disaster victims from a floodplain area in Lapland to a safer area in Ward 48 are progressing well.
The initial delay was caused by an application for approval by the Department of Forestry, Fisheries, and the Environment on the residential usage of the identified land, which we have since received with conditions. Executive Mayor Gary van Niekerk said even though the department gave the go-ahead two weeks ago, the permission came with a caveat.
“The condition was that the Metro must appoint an Environmental Specialist to monitor and guide work to clear the building site as well as the relocation and erection of temporary housing structures.
“The supply chain process to appoint this specialist started immediately after the go-ahead from the department was received, resulting in the tender process being concluded this week, Tuesday, 20 August 2024.
“The appointment of the specialist will now follow and should not take longer than the anticipated two weeks,” Mayor Van Niekerk said.
Following the flood, the people of Lapland were moved to temporary accommodation in the town of Kariega. After the floodwater subsided, they went back to their area to wait for the iminent relocation.
In Walmer, the flood victims are waiting for the electrification of temporary housing structures before they can be relocated. Availability of stock for electrification is causing the delays. Intervention measures have been put in place to speed up the process.
NMB Communications
Latest posts by NMB Communications (see all)
- Join The Celebration - 26 February 2025
- 6 Municipal Employees Supended - 15 January 2025
- Fishwater Flats Wastewater Treatment Plant Work Progressing Well - 10 January 2025
- Kliprand Protest Brings Action - 7 January 2025
- Mayor Tells Us Why We Had a Successful Festive Season in Nelson Mandela Bay - 6 January 2025