A high voltage circuit breaker blew at the Humewood sub-station, situated at the corner of La Roche Drive and Humewood Road on Saturday morning, 18 June and as a result areas in the vicinity of La Roche Drive as well as San Antonio, Glenton Heights, Kings Beach, Playland and Elizabeth Hotel will be without electricity until Wednesday.
Circuit breakers are designed to absorb the impact when something goes wrong at a substation. A clean-up operation is currently taking place in preparation of repair work to the substation.
The difficulty is exacerbated by the fact that the high voltage circuit breakers will have to be ordered from Middelburg/Cape Town as the whole sub-station must be refurbished. Transport and delivery time must be taken into account.
However, the municipality is currently investigating the possibility of getting temporary electricity supply to the Humewood sub-station before Wednesday to restore electricity supply to all the affected consumers.
The following substations are off: Mutualhof, Elmdor, San Antonio, Grante Heights, San Remo, Pendennis, Local Lelane, Elizabeth and Cathcart Mini.
The Nelson Mandela Bay Municipality would like to apologize for the inconvenience caused by this unforeseen incident.
NMB Communications
Latest posts by NMB Communications (see all)
- Join The Celebration - 26 February 2025
- 6 Municipal Employees Supended - 15 January 2025
- Fishwater Flats Wastewater Treatment Plant Work Progressing Well - 10 January 2025
- Kliprand Protest Brings Action - 7 January 2025
- Mayor Tells Us Why We Had a Successful Festive Season in Nelson Mandela Bay - 6 January 2025