The Nelson Mandela Bay Municipality’s R46million ground water supply project at the St George’s Park has been successfully completed and commissioned, giving much needed reprieve to the depleting local dams that supply water to the Port of Port Elizabeth, Central and Humewood amongst other areas.
The project, which commenced from July 2021, is one of the Municipality’s water augmentation projects, which seek to ensure that Nelson Mandela Bay does not run out of water.
With a total of four boreholes constructed, the St George’s Park Wellfield construction work included:
- Construction of a treatment works and discharge pipework
- Construction of a pump station and a pressurized pipeline
- Installation of mechanical, electrical, and electronic equipment
- Installation of a collector pipeline to convey groundwater to a centralized point Bulk earthworks and trenching
- Tie into existing NMBM bulk water network, and. Commissioning of groundwater monitoring system.
During the official opening of the Wellfield, NMBM Deputy Executive Mayor, Cllr Mkhuseli Jack, said: “The Municipality is doing all it can to ensure that we maximise all our resources as we continue to face a dire situation of no rainfall. While we continue to do our part, we need all our residents to work with us and play their part. We can not win this battle we are faced with alone. We opened the first boreholes project in November last year, this site is our second one and we still have two more sites we will commission later this year.”
“We are really doing our best to make sure that residents and businesses have water supplied to them. We will be receiving an average of 2.1 million litres of water from this site alone. The water is treated and safe to drink. Not only will this site supply the areas that are serviced by the St George’s Park reservoir, but through the constructed pump station the Wellfield will feed other reservoirs connected to the Churchill pipeline.”
The levels of the major storage dams supplying the Metro can be seen here: Dam Levels
As the Municipality continues to urge residents and businesses to drastically reduce water consumption, Drought Crisis Public meetings commenced from 9 March to 5 April 2023. Residents are encouraged to attend these sessions as Executive Mayor, Cllr Retief Odendaal, his Mayoral Committee members and top Infrastructure and Engineering officials will answer burning questions concerning the drought crisis.
Views Since 15 July 2022: 54
Gqeberha’s Latest News and Events can be accessed on MyGqeberha.com.
The following two tabs change content below.
Alan Straton
Chief Cook, Bottle Washer and Broom Mechanic at MyPE
Passionate about Port Elizabeth and definitely NOT packing for Perth.
Alan's ethos is epitomised in the words of Nelson Mandela; "I have fought against white domination and I have fought against black domination. I have cherished the idea of a democratic and free society. If need be, it is an ideal for which I am prepared to die."
See more articles by Alan.
Latest posts by Alan Straton (see all)
-
Decor Handles Spotlights Its Solid Brass Door Handles From Portugal and Italy - 14 November 2026
-
PaperTrail Puts a Risk Score on Every Contract With Scout AI - 14 November 2026
-
Pay@ Puts Automatic Reconciliation at the Centre of Year-End Collections - 13 November 2026
-
Renal Supplies Water Systems Plans Dialysis RO Plants From Tap to Drain - 13 November 2026
-
MoreCut Saws in Alrode Welds Bandsaw Blades to the Length Your Saw Needs - 13 November 2026
Alan Straton
Latest posts by Alan Straton (see all)
- Decor Handles Spotlights Its Solid Brass Door Handles From Portugal and Italy - 14 November 2026
- PaperTrail Puts a Risk Score on Every Contract With Scout AI - 14 November 2026
- Pay@ Puts Automatic Reconciliation at the Centre of Year-End Collections - 13 November 2026
- Renal Supplies Water Systems Plans Dialysis RO Plants From Tap to Drain - 13 November 2026
- MoreCut Saws in Alrode Welds Bandsaw Blades to the Length Your Saw Needs - 13 November 2026