• Skip to main content
  • Skip to footer
  • Home
  • About
    • MyPE Copyright Terms
    • Authors
    • Deals
  • Info
    • Accommodation
    • Classified Adverts
    • Directory
    • Essential PE Numbers
    • Flight Schedules
    • Forex Converter
    • PE’s Online Radio Stations
      • Algoa FM
      • Bay FM
      • iFM
      • Kingfisher FM
      • MannMade Radio
      • Madibaz Radio
      • Umhlobo Wenene
    • Podcasts
    • Shipping
    • Street Map
    • Tides
    • Ward Details
    • Ward News
    • Weather
  • Contact
    • Advertising on MyPE
  • Submit
    • Blogger
    • 5 Quick PE Questions
    • Entertainment
    • Events
      • Add your Port Elizabeth event
    • Letter to the Editor
    • Lost and Found
    • Movers and Shakers
    • News Article
    • PE Videos
    • Photographs
    • Recipes
    • Traffic Hooligan
    • Say NO
  • Dam Levels
  • Advertorial
  • Business
  • NMBRA
  • NMB Rates
MyPE

MyPE

Community Business Directory, Event Listings, News and Views from Gqeberha, Nelson Mandela Bay

Eskom must suspend Request for Proposals

25 November 2016 By Port Elizabethan

Dear Editor

The DA will be writing to both Minister Joematt-Pettersson and Minister Brown demanding that they halt any attempt by Eskom to proceed with the issuance of the Request For Proposal (RFP) for nuclear until such a time as the Integrated Resource Plan (IRP) and the Integrated Energy Plan (IEP) – the pillars of South Africa’s energy policy – have passed public consultation and have been adopted by Parliament.

Eskom’s announcement today that they plan to issue the RFP by the end of the month flies in the face of logic and national energy policy – detailed and made public by the Department of Energy yesterday in drafts of the IRP and IEP. The plans together provide a legal and statutory framework for determining energy policy to 2050.

Although not without fault, the IRP 2016 has been extensively modelled and clearly indicates that an urgent acquisition of an additional nuclear base load capacity of 9,6GW is neither urgent or necessary. The base case scenario – which assesses energy demand for the period 2050 indicates that additional nuclear base load power will only be required by the mid-2030s meaning procurement should only commence in the early 2020s.

Given this extended timeline, it is grossly premature and potentially irrational for Eskom and master of the dark arts – Mr Matshele Koko, Eskom spin doctor in Chief – to call fall the finalisation and issuance of the RFP by the end of the month.

An RFP, issued on the basis of an outdated and legally dubious Section 34 Ministerial determination, itself based on the much maligned and now out of date IRP 2010, would be subject to legal challenge court of law.

It is clear Eskom would struggle to demonstrate that its decision to procure additional nuclear capacity contrary to national energy policy contained in the IRP 2016, is rotational or justifiable. The Constitutional Court has ruled that for State action to be determined valid it must pass the test of rationality.

It is glaringly obvious that the rush to conclude the nuclear deal is only rational for those who stand to loot the state coffers ie. President Zuma and his Gupta cronies.

The RFP for the deal must be halted in the interest of the many South Africans who will suffer as this deal will ultimately destroy our already ailing economy.
 
Regards

Gordon Mackay MP
DA Shadow Minister of Energy

The following two tabs change content below.
  • Bio
  • Latest Posts

Port Elizabethan

This author is a 'catch-all' for occasional articles and letters written to MyPE. The Author of each article can be found in the signature at the bottom of each individual article.

Latest posts by Port Elizabethan (see all)

  • Why Fewer People Are Being Convicted for Commercial Crimes - 15 May 2026
  • Urgent Call for South Africa to Support and Join Global Efforts to Phase Out Fossil Fuels - 15 April 2026
  • Unfenced 6 SAI Army Base Outside Makhanda Claims Another Life - 20 November 2025
  • Death Toll Rises From Makhado Bus Crash - 21 October 2025
  • Law Clinics Flooded as Home Affairs Blocks Asylum Seekers From the System - 15 October 2025

Filed Under: Letters to the Editor Tagged With: eskom, Gordon Mackay

Footer

RSS Straton Electrical

  • Open Cycle Gas Turbine Usage
  • Flattening the curve – What Every Solar Installer Needs to Know
  • Why you shouldn’t leave a charger plugged in when not in use
  • How do I check if an Electrician is properly registered in South Africa?
  • Easy Electrical Troubleshooting for Humans
  • Water – If You Cannot Measure It Then You Cannot Manage It
  • Tips To Survive Loadshedding
  • Eskom’s Top 50 Electricity Saving Tips

RSS MyPE Business News

  • NMBBC On Budget 2025
  • Leading Business Minds Set to Headline Chambers Annual General Meeting
  • Bay of Opportunity Portal
  • Bay of Opportunity Ambassadors Programme to Promote the Bay and Attract Investment
  • 6 Decades of Trucking
  • Thermal Camera Installed at Redhouse Substation
  • Finalist in the 2025 South African Car of the Year
  • Joining hands to create a lasting impact to St Albans Primary School

RSS MyPR Press Releases

How you may use MyPE content © 2026 MyPE · Gqeberha, South Africa | Privacy Policy | MyPE Ads and Media Kit