Work continues at the BAIC SA Manufacturing Plant – bush clearing completed by 11 SMMEs – on track to start production in 2018, with maximum participation of the local SMMEs. Phase 1 (Site Preparations) has been completed and Phase 2 (Construction) is due to start soon; however excavations are already underway.
Today, the Coega Development Corporation (CDC) announced that the BAIC SA investment in the manufacturing facility is earmarked to be completed within the planned timeframes. However, to achieve this, the construction of the Chinese automaker’s plant will have to be accelerated.
During Phase 1 of the project (SITE PREPARATION), managed by the CDC directly, 11 Small, Medium and Micro Enterprises (SMMEs) have benefited from the BAIC SA Investment in the Coega SEZ. The other phases of the project including Construction would be coordinated and project managed directly by the IDC and BAIC SA through their appointed company.
The 11 SMMEs cleared the 54.62 hectares of land in Zone 1 of the Coega Special Economic Zone (SEZ), built the BAIC SA Plant Platform, and provided Plant Hire equipment.
The aforementioned SMMEs involved during phase 1 were 100% Black Owned, and 2 Women Owned Entities. The total value of the initial contract was R17.1million.
In view of the opportunity provided, local SMMEs have expressed satisfaction with the progress made during phase 1 in terms of participation.
The SITE PREPARATION entails:
- Geotechnical investigations – Completed
- Site Survey – Completed
- Search & Rescue of plants – Completed
- Bush Clearance – Completed
- Platform – Completed
BAIC Infrastructure:
- Ring Road (Design) – on procurement (SMMEs to be allocated 36.25% of project value)
- Electrical 132kv Line (Tender) – Design & Construct to be allocated 38% SMME packages for the construction component post tender.
- Fire Water Supply (Design) – on procurement(SMMEs to be allocated 36.25% of project value)
- Currently, on site, BAIC SA is busy with the excavations in preparation for the building of grid lines for steel structures.
It is expected that BAIC SA and IDC will announce the start of construction soon (Phase 2- CONSTRUCTION)
Alan Straton
Latest posts by Alan Straton (see all)
- Early Signs of HIV And Why Testing Matters - 27 November 2026
- Just Some Tools Packs Six Clamps and a Pressure Card for Highveld Glue-Ups - 26 November 2026
- Phase Converters Sets Out How to Size a Rotary Unit From the Motor Plate - 26 November 2026
- Set-IP Puts Trade Mark Renewal Dates on a One-Page Wall Sheet for Makers - 26 November 2026
- Colour Planet Adds Catalogue Printing to Its Pinetown Litho Line - 26 November 2026